Bheramara 410MW Combined Cycle Power Plant

Bheramara 410MW Combined Cycle Power Plant

Power Plant Location Bahirchar, Bheramara, Kushtia
Executive Agency North West Power Generation Company Limited (A representative of Bangladesh Power Development Board)
EPC Contractor M/s. Marubeni Corporation, Japan
Financer GOB & JICA
EPC Cost Eqv. Tk. 251,998 Lac (USD: 178,788,328 ;
JPY: 10,237,497,008 ; BDT: 2,562,922,636 ;
EUR: 8,510,300)
Total Project Cost Tk. 414,048 Lac (GOB: Tk. 91,939.59 Lac + PA: Tk. 322,108.42 Lac)
EPC Contract Signing Date 16/03/2014
Manufacturer of GT and ST Mitsubishi Hitachi Power Systems (MHPS)
Fuel Type Dual Fuel (Natural Gas + HSD)
Production Capacity 410 Megawatt
Commercial Operation Date(Completed) 09/05/2017 (Simple Cycle), 14/12/2017 (Combined Cycle)