Khulna 225 MW Combined Cycle Power Plant

Khulna 225 MW Combined Cycle Power Plant

Power Plant Location Goalpara, Khalishpur, Khulna
Executive Agency North-West Power Generation Company Limited
EPC Contractor M/s. Isolux Ingenieria S.A.- Initec Energia S.A. JV, Spain & M/s. CCC-ETERN-CCCE JV, China (Simple Cycle),
M/s Shanghai Electric Group Co. Ltd, China (SEC) (Combined Cycle)
Financer ADB, GOB
EPC Cost USD 190.86 Million
Total Project Cost GOB: BDT 116,490.39 Lac plus
PA: BDT 137,528.35 Lac plus
NWPGCL: BDT 208.39 Lac
EPC Contract Signing Date 12 May, 2011 (Simple Cycle),
05 March, 2014 (Combined Cycle)
Manufacturer of GT and ST ALSTOM, Switzerland (GT),
M/s Shanghai Electric Group Co. Ltd, China (SEC) (ST)
Fuel Type Primary – HSD, Alternative – Natural Gas
Generation Capacity 230 MW
Commercial Operation Date 23 Sep, 2013 (Simple Cycle),
25 June, 2016 (Combined Cycle)