Sirajganj 225 MW Combined Cycle Power Plant (3rd Unit)

Sirajganj 225 MW Combined Cycle Power Plant (3rd Unit)

Project Location Soydabad, Sirajganj
Executive Agency North-West Power Generation Company Limited
Plant Type Combined Cycle Gas Turbine
EPC Contractor Consortium of M/s. China National Machinery Import & Export Corporation (CMC), China and Fujian Electric Power Survey & Design Institute (FEDI), China
Date of EPC Contract 12 July, 2015
Effective Date of EPC Contract 27 March, 2017
EPC Contract Price USD 118,874,214.00 + Euro 35,200,000.00 + BDT 155,950,015.00
(upto Amendment-1)
Fuel Type Primary – Natural Gas, Alternative – HSD
Generation Capacity 220
Mode of Financing ECA Finance (100% on EPC)
Date of Power Generation Project Proposal (PGPP) Approval 05 April, 2015
Total Estimated Project Cost and Financing Plan (As per PGPP) 236.22 M USD (Equ. BDT 182,856.87) (1USD =77.41 BDT)
Name of ECA Financer Standard Chartered Bank (SCB)
Date of Financial Agreement 28 November, 2016
Name of Engineering Consultant Minconsult Sdn. Bhd., Malaysia
Date of Engineering Consultancy Services Contract 17 May, 2016
Commercial Operation Date(Completed) Simple Cycle: Dec, 2018
As per Contract : Achived on 09 August, 2018
Combined Cycle: As per Contract: Sep, 2019
Expected: Dec, 2018