Sirajganj 225 MW Combined Cycle Power Plant (Unit-3)

Sirajganj 225 MW Combined Cycle Power Plant (Unit-3)

Power Plant Location Soydabad, Sirajganj
Executive Agency North-West Power Generation Company Limited
EPC Contractor Consortium of M/s. China National Machinery Import & Export Corporation (CMC), China and Fujian Electric Power Survey & Design Institute (FEDI), China
Financer Standard Chartered Bank (SCB)
(ECA)
EPC Cost USD 164.12 Million
Total Project Cost USD 236.22 Million (Equ. BDT 182,856.87) (1USD=77.41 BDT)
EPC Contract Signing Date 12 July, 2015
Manufacturer of GT and ST Siemens (GT)
Dongfang Electric Machinery Co. Ltd. (ST)
Fuel Type Primary - Natural Gas, Alternative - HSD
Generation Capacity 220 MW
Commercial Operation Date Simple Cycle: 09 Aug 2018
Combined Cycle: December 2018 (Expected)