1 Contract Signing for Engineering Consultancy Services of Sirajganj 225 MW CCPP Project (3 rd Unit) 17-05-2016
2 COD of Upgradation of Khulna 150 MW PPP to 225MW CCPP Project 28-06-2016
3 Signing of Amended Subsidiary Loan Agreement for Sirajganj 150 MW Power Plant and Khulna 150MW Power Plant 27-07-2016
4 Contract Signing for Consultancy Services for Environmental Impact Assessment(EIA) and Resettlement Plan(RP) of Khulna 800 MW LNG Based Combined Cycle Power Plan Project. 23-08-2016
5 Contract Signing for Consultancy Services for Legal Experts in connection with the development and finalization of Gas Sales Agreement(GSA) for the importation of Regasified LNG (R-LNG) from India for the proposed Khulna 800 MW LNG Based Combined Cycle Power Plant Project. 24-08-2016
6 Financial Agreement Signing Between BCPCL and CEXIM Bank on 14/10/2016 at the Prime Minister's Office in Presence of Honorable Prime Minister of People's Republic of Bangladesh Sheikh Hasina and Honorable President of People's Republic of China Xi Jinping. 14-10-2016
7 Gas Service Agreement on the 13th of March, 2017 between Sunderban Gas Company Limited (SGCL) & North-West Power Generation Company Limited. 13-03-2017
8 MOU Signing between NWPGCL & SGCL for gas supply to Rupsha 800 MW Combined Cycle Power Plant Project on 30-04-2017 at NWPGCL's Corporate office, Bidyut Bhaban, Dhaka 30-04-2017
9 Power deal of the year at the Asset Triple A- Asia Infrastructure Award 2017 received by North-West Power Generation Company Ltd. for Sirajganj 225 MW Combined Cycle Power Plant Project (3rd Unit) on 28 June 2017. 28-06-2017
10 Simple Cycle of Sirajganj 225 MW Combined Cycle Power Plant(2ndUnit-Dual Fuel) was synchronized with National Grid on 02-08-2017 02-08-2017