Khulna 150 MW Power Plant has started its operation on 24/10/2013. NWPGCL signed power purchase agreement (PPA) with Bangladesh Power Development Board on 04/12/2013. Under this power purchase agreement BPDB purchase electricity from Khulna 150 MW Power Plant.

Khulna 150 MW Power Plant

Project Location Goalpara, Khalishpur, Khulna
Executive Agency North-West Power Generation Co. Ltd. (NWPGCL)
Financer GOB & ADB
EPC Contractor M/s. Isolux Ingenieria S.A.- Initec Energia S.A. JV, Spain & M/s. CCC-ETERN-CCCE JV, China
EPC Cost BDT 11,148.91 Million
Total Project Cost BDT 15,422.37 Million
Fuel Type Primary – Natural Gas, Alternative – HSD
Manufacturer of GTG ALSTOM, Switzerland
EPC Contract Signing Date 12 May, 2011
Commercial Operation Date(Completed) 24 Oct, 2013

Upgradation of Khulna 150 MW Power Plant to 230 MW CCPP

Project Location Goalpara, Khalishpur, Khulna
Executive Agency North-West Power Generation Company Limited
(An Enterprise of Bangladesh Power Development Board)
Financer ADB, GOB & NWPGCL
EPC Contractor M/s Shanghai Electric Group Co. Ltd, China (SEC)
Fuel Type Not required (Flue Gas of GT will be used)
EPC Contract Signing Date 05 March, 2014
Project Cost BDT 731.73 Crore
Commercial Operation Date 25 June, 2016