Updated: Up to October, 2017

<
SL Name of the Project Fuel Capacity
MW
Expected COD Status
1 Bheramara CCPP (360 MW) Development Project (Steam Turbine) No additional Fuel 132
December, 2017(CC)
Details
2 Sirajganj 225 MW Combined Cycle Power Plant Project (2nd Unit) Natural Gas/ HSD 220 December, 2017 Details
3 Sirajganj 225 MW Combined Cycle Power Plant Project (3rd Unit) Natural Gas/ HSD 220 March, 2018 (SC)
Sep, 2018 (CC)
Details
4 Sirajganj 400 MW (±10%) Combined Cycle Power Plant Project Natural Gas/HSD 220 Mar, 2018 (SC)
Sep, 2018 (CC)
Details
5 Payra 1320 MW Thermal Power Plant Project Imported Coal 1320 April, 2019 (1st Unit)
October, 2019 (2nd Unit)
Details
6 Madhumati 100 MW HFO Based Power Plant Project HFO 100 October, 2018
7 Rupsha 800 MW Combined Cycle Power Plant Project Natural Gas/ HSD 800 December, 2019 (1st Unit)
September, 2020 (2nd Unit)
Total 3206