Future Projects

To meet the future challenges of demand of electricity of Bangladesh at affordable cost with minimum environmental impact, the Company has drawn a long-term technology-oriented roadmap.

Future Projects

SN Name of the Project Fuel Capacity (MW) Expected COD Status
1 Payra 50 MW Wind Power Plant Project (Under JVC) Wind 50 December 2022 Details
2 Sirajganj 100 MW Grid Connected Photovoltaic Solar Power Plant Project (Under JVC) Solar 100 June 2022 Details
3 Dighipara 1000 MW Ultra Super Critical Thermal Power Plant Project (Under JVC) Domestic Coal 1000 June 2025 Details
Total 1150

Name of the Project:

Payra 50 MW Wind Power Plant Project (Under JVC)

Present Status:

  • প্রকল্পের Feasibility Study M/s. FEDI, China কর্তৃক চলমান রয়েছে। বায়ু পরিমাপের জন্য 120 মিঃ Tower Erection, আনুষঙ্গিক যন্ত্রপাতি ও সেন্সর বসানোর কাজ সম্পন্ন হয়েছে এবং Data Collection and Analysis-এর কাজ চলছে।

    Updated: Up to October 2019

Name of the Project:

Sirajganj 100 MWp Grid Connected Photovoltaic Solar Power Plant Project (Under JVC)

Present Status:

  • প্রকল্পটি বাস্তবায়নের জন্য ‘বাংলাদেশ সেতু কর্তৃপক্ষ’-এর আওতাধীন বঙ্গবন্ধু সেতু সংলগ্ন ৩৩০ একর জমি ইজারা নেওয়ার লক্ষ্যে ইতোমধ্যে ‘বাংলাদেশ সেতু কর্তৃপক্ষ’ বরাবর পত্র প্রেরণ করা হয়েছে।
  • M/s. FEDI, China কর্তৃক প্রকল্পের Draft Feasibility Study Report প্রস্তুত করা হয়েছে। শীঘ্রই Feasibility Study সম্পন্ন হবে বলে আশা করা যায়।

       Updated: Up to October 2019

Name of the Project:

Dighipara 1000 MW Ultra Super Critical Thermal Power Plant Project (Under JVC)

Present Status:

  • পরিকল্পনাধীন
Updated: Up to October 2019